In 2024, Uzbekistan sold 100,000 tons of copper raw materials through the exchange, of which 85,300 tons were processed, resulting in products worth 9.4 trillion sums.
The "Angren Pipe Plant" specializes in processing copper raw materials to produce copper pipes of various diameters. In 2024, the plant processed 7,500 tons of copper, with 95% of the produced goods being exported. In the same year, the company began exporting its products to European markets.
In 2025, the company plans to process 12,000 tons of copper raw materials and export 10,000 tons of copper products.
The plant was established in 2013 in the Tashkent region within the special industrial zone "Angren." The project's capacity ranges from 5,000 to 8,000 tons per year. The primary raw material is cathode copper with a purity of 99.99% (according to GOST 5462001), supplied by JSC "Almalyk Mining and Metallurgical Complex." The produced goods are primarily aimed at export (85%) and also cater to the domestic market (15%).